COMMENTS ON
REGULATIONS UNDER SECTION 141
OF THE CODE AS THEY RELATE TO OUTPUT FACILITIES
Part VIII | Part VIIIc | Part VIIId | Part VIIIf | Part
VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3 | Contents
COMMENTS AFFECTING
GENERATION AND TRANSMISSION
Definition of Output Contract
The general rule relating to output contracts under § 1.141-7T(c)(1) should be amended
by inserting the phrase "pursuant to a contract" in the first sentence after
"The purchase." As it is, the defined term "output contract" has no
antecedent.
Contracts With Specific Performance Rights
Section 1.141-7T(c)(5) of the Temporary Regulations provides that an output contract
that provides the purchaser with specific rights to control the output of a facility or
with other specific performance rights to the use of output of a facility is generally
taken into account even if the issuer does not reasonably expect that it is substantially
certain that payments will be made under the contract; however, a customers normal
entitlement to receive utility service (for example, an entitlement to reasonable
protection against blackouts in times of high demand through rotating the effect of
blackouts) is not treated as a specific performance right for this purpose.
We do not understand what specific performance rights are. If they are intended to
cover preferential rights to output, that concept is already covered in the benefits
portion of the benefits and burdens test, making the specific performance rights rule
redundant.
Former IRS personnel have explained that this rule reflects the notion that contracts
resembling leases should be subject to a more restrictive standard than simple contracts
for service. We agree with this notion. We suggest, however, that the specific performance
standard alone is not reflective of the nature of a contract as a lease, as well as being
uncertain as to its meaning. If the theory is to treat contracts resembling leases as
leases, the Code already provides section 7701(e) for that purpose. Concepts from that
section should be used, rather than a vague and novel specific performance standard.
In many plants with joint ownership, the operator of the plant is also a purchaser of
some of a municipal participants output from the facility. Typically such purchases
would be under take or take or pay contracts and would be counted in any event. In some
instances, however, the operator may purchase surplus energy from the municipal
participant to the extent it is available. If the effect of this provision is to require
that those purchases be taken into account because of the de facto control of the
operator, it would be a radical departure from existing law that would preclude a party
from such a contract from opting into the Temporary Regulations. If this test is retained,
it should be modified to clarify that it does not apply by reason of an agreement to
manage or dispatch a plant owned by multiple participants in accordance with prudent
utility practice.
Part VIII | Part VIIIc | Part VIIId | Part VIIIf | Part
VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3
Short-Term Contract Safe Harbor
Under the Temporary Regulations, the time limitation on sales that are treated as
"uses" of the facility are the same as they would be if the purchaser of the
output actually leased the plant, used its employees to operate it and sold the output,
even if in fact the purchaser of the output pays a market price, has no involvement in the
operation or financing of the plant, has no participation in the profits or cost savings
from its operation and has no risk of loss with respect to the plant. There is no other
area of tax law in which it could even be imagined that a purchase of service on such
terms for a period of 31, 91 or 181 days might be treated as a use of the facility or the
funds that financed it, and there is nothing in the 1986 Act that supports reaching that
result simply because property is governmentally owned. By contrast, an investor-owned
utility has been allowed to purchase 41 percent of the output of a facility owned by a
cooperative for a term of 15 years under a "take" contract without any portion
of the facility becoming public utility property.29
PLR 8521163 (Feb. 28, 1985).
It is sometimes suggested that any purchase of output from an output facility is a use
because the output is the only value produced by the facility. That reasoning is
fallacious. As previously noted, the provisions of the Code denying investment credits and
limiting depreciation deductions for property used by tax-exempt entities (including
governmental entities) stem from policy concerns that are comparable to the limitations on
private use in the tax-exempt financing area. Yet no one has suggested that a government
contractor that uses its plant to produce widgets for the government, or a manufacturer
that sells to a tax-exempt entity under a 61-day contract, should lose tax benefits
associated with the plant, even if the contract is a cost plus contract. Ford does not
lose tax benefits just because half its Crown Victorias are sold to the police pursuant to
contracts. A payroll service does not lose a portion of the tax benefits associated with
its computers because it has contracts with governments or 501(c)(3) organizations. The
mere purchase of output from a plant is not the use of the plant.
We think a common sense approach should be applied to the short-term use of output
facilities. In particular, without specifying the exact outlines of what constitutes use,
we believe a contract that (1) is of a relatively short term duration, such as 3-5 years,
(2) is at an arms length market or tariff price rather than direct cost pass-through
price, (3) was not a material factor in the financing of a facility and (4) gives the
purchaser of the output no possessory interest or ability to control the manner of
operation of a facility cannot be considered to give rise to use of the facility on any
reasonable basis and that a safe harbor should be established along those lines.
In that connection, we note that the economic beneficiary of any contract of the nature
described would not be the purchaser under the contract, who would be paying an arms
length price. Rather, the benefit would go to the other customers of the MOU, whose rates
would otherwise be increased to pay the fixed costs of unused capacity.
Short-Term Contract Limits Should Treat
All Months Equally. The 30 day, 90 day and 180 day safe harbors should be
changed to one month, three months and six months. It is impossible to explain to clients
that they can make sales for some months, but not others.
Other Transactions. Other
transactions that should not give rise to private use include seasonal sales, typically
for one or more 6-month periods that do not take the form of swaps and thus do not qualify
for the swapped output exception, and sales of excess energy, including sales of so-called
financially firm energy30
at arms-length rates for limited periods. These transactions in no sense pass to the
purchaser the benefits of ownership or burdens of paying debt service, substantial or
otherwise.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part
VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3
De Minimis Contracts
The rule of the 1994 Proposed Regulations was a reasonable approach. It scaled down the
3 percent rule in proportion to the reduction in permissible private use from 25 percent
to 10 percent. In addition, it explicitly recognized what was implicit in the term
"annually" in the Subparagraph 5 Regulations: that the average annual guaranteed
payment during the contract term should be compared to the average annual debt service.
By reducing the limit to half of one percent, making it a comparison between the
payment in any one year and the average annual debt service, by (perhaps inadvertently)
suggesting that it be compared to debt service on any bond issue or at best leaving this
issue vague, and by requiring that these miniscule payments be evaluated to determine if
they are substantially certain, the Service has created a nullity.
The rule of the 1994 Proposed Regulations should be adopted, but should be limited to
"guaranteed minimum payments."
Relationship to Payments Test.
Given the reliance placed by the Temporary Regulations on Reg. § 1.141-4 (see §
1.141-7T(e)), the de minimis rule should explicitly state that Reg. § 1.141-4(c)
is to be applied before application of the de minimis rule. Thus, payments should
be allocated to O&M as well as sources of funding before determining whether the
payments allocable to particular bonds meets the de minimis threshold.
Rules Regarding Measurement Period
The Temporary Regulations provide that "the rules of 1.141-3(g)" are used to
determine the measurement period, thus replacing the "contract term" concept of
the Subparagraph 5 Regulations. It appears that the reference should be to section
1.141-3(g)(2), since most of the other portions of section 1.141-3(g) deal with subjects
other than the "measurement period" or deal with subjects that are covered by
the concept of available output. Moreover, the provisions of section 1.141-3(g)(7) should
not apply to output facilities. Under that provision, if an issuer enters into an
arrangement for private use of a facility a substantial period (10 percent of the
measurement period) before the right to actual private use commences, and "the
arrangement is an arrangement for ...long term use," the measurement period begins on
the date the arrangement is entered into. Under this rule, an issuer issuing 30 year bonds
to finance a facility with a three year construction period and having an agreement from
the beginning to sell 20 percent of the output of the facility for 13.5 years (10 percent
of the available output over the term of the bonds) in a transaction giving rise to
private use would apparently exceed the permissible limit because the construction period
would count as private use. That result is inappropriate. We note that Example 1 of
section 1.141-7T(h) of the Temporary Regulations, where 25 year bonds are issued to
finance a facility with a four year construction period, correctly ignores the application
of section 1.1413(g)(7).
Under section 1.141-3(g)(2)(i), the measurement period ends on the earlier of the
maturity date of the latest maturity date of any bond of the issue that financed the
facility or the reasonably expected economic life of the facility. Output facilities are
often financed with more than one issue, each of which has a different final maturity. As
a result, there may be different private activity limits for the same facility for each
issue.31 This complexity could be avoided
if the last maturity of any issue financing the facility were used for all issues
financing that facility. The anti-abuse rule of section 1.141-3(g)(2)(v) should protect
against manipulation through multiple issues.
"The reasonably expected economic life" of the facility is to be determined
"as of the issue date." This should be the issue date of the first substantial
issue of obligations issued to finance the facility. It should not be retested in the
event of a refunding of one or more of the issues. See "Time for Applying Rules
Involuntary Charges," above.
The special rule of section 1.141-(g)(2)(iii) for reasonably expected mandatory
redemptions is discussed below under "COMMENTS REGARDING REMEDIAL ACTION."
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part VIIIh
| Part VIIIi | Part VIIIj | Part
VIIIj3
Application of the Payments and Security Tests
The Temporary Regulations provide that the measurement of payments made or to be made
by nongovernmental persons under output contracts as a percentage of debt service is
determined under the rules provided in section 1.141-4. Section 1.141-4(c)(2) provides
that payments for a use of property include payments (whether or not to the issuer) in
respect of property financed directly or indirectly with those proceeds "even if not
made by a private business user." This rule is sensible in the context of a bond
financed facility subject to a "bad" management contract; in such a case, since
the manager in effect has the benefits and burdens of ownership, it is as if the payments
by the general public are the managers payments. This rule, however, should not be
applied where, for example, a private user is taking 20 percent of the output of a bond
financed facility but is only making payments equal to 10 percent of debt service, to
treat an additional 10 percent paid by the general public as private payments. To
interpret the rule in that fashion would render the payments test a nullity. In the past,
the regulations have never articulated a basis for different treatment of general public
payments in the management contract context as opposed to the output context. The reason
for the difference is that in the management contract situation the particular facility is
entirely privately used by reason of the management contract, and the general public is
making payments for its use of the very property that is privately used. By contrast, in
the output context, where the general public makes payments with respect to output, it is
only with respect to the output of the portion of the facility that is not being used by a
private user. Thus, such payments should not be considered private payments. The
regulations should articulate this difference.
Allocation of Payments to Debt Service
There are several different rules regarding the amount of payments that must be taken
into account. Under section 1.141-4(c)(2)(i)(B), payments are not taken into account to
the extent that the present value of those payments exceeds the present value of debt
service on the proceeds being used. Thus, if a purchaser is using 10 percent of the output
of a facility for the first 10 percent of the life of the facility, the payments taken
into account would not exceed an amount equal to 10 percent of debt service during that
period. Under section 1.141-4(c)(2)(i)(C), payments by a person for a use of proceeds do
not include the portion of any payment that is properly allocable to the operation and
maintenance of the financed property used by that person, but operation and maintenance do
not include general overhead and administrative expenses. Accordingly, if the contract
referred to above required the purchaser to pay for 10 percent of all costs, including
general overhead and administrative, the overhead and administrative payments would not be
excluded under section 1.141-4(c)(2)(i)(C), but they would be excluded under section
1.141-4(c)(2)(i)(B). If, on the other hand, the contract required the purchaser to pay 80
percent of 10 percent of all costs, and 20 percent of the costs were overhead and
administrative, the payments allocable to debt service would include the full amount of
debt service even though that was not the agreement of the parties. In other words, even
though the parties had agreed that the purchaser would only pay 80 percent of the actual
costs, including debt service, the regulation would allocate payments to debt service in
the full amount of debt service.
In addition, output contracts frequently call for separate charges for energy and
capacity. Since capacity charges are fixed and energy charges vary with the energy taken,
the allocations can generally be relied on to determine the payments that should be
counted under the payment test.
There are well established rules for accounting for costs in the electric industry. We
think an issuer should be able to use those rules in determining the amount of payments
allocable to debt service.
Under section 1.141-4(c)(3)(iv), payments made under an arrangement entered into in
connection with the issuance of bonds are generally allocable to that issue. Presumably,
this rule does not change the amounts of payments that are taken into account, as
described above.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part
VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3
Allocation to Equity Financed Portion of a
Facility
The Temporary Regulations also indicate that where facilities have been financed with
multiple funding sources, the allocation rules provided in the 1997 Final Regulations may
be utilized to allocate private use and private payments. These rules generally provide
for pro rata allocations to sources. We are concerned that these rules foreshadow a rule
that private sales might have to be allocated pro rata to the equity and debt financed
portions of facilities. Clarification is needed that, where private sales are allocated to
a particular unit that has been partly financed with bond proceeds and partly financed
with equity, the "bad" sales may be allocated to the equity-financed portion of
the facility. Such a result is consistent with Congress intent as reflected in the
1986 Tax Act legislative history, which effectively treated the private use and
governmental use portions of facilities as separate facilities. Thus, the Conference
Report states that, where 10% of the output of a $500,000,000 facility is to be sold to an
IOU, $465,000,000 of tax-exempt debt can be issued to finance the facility. If the private
sales had to be allocated pro-rata to tax-exempt debt and equity, only $150,000,000 of
bonds could have been issued without exceeding the $15,000,000 limit. The example only
works where the private sales are allocated first to equity. The example is properly
reflected in the example in section 1.141-8T(c) of the Temporary Regulations. Thus, both
Congress and the IRS have recognized that private sales can be allocated first to equity.
Clarification also would be useful with respect to the allocation of private payments
from bad contracts. The Temporary Regulations refer to the rules of the 1997 Final
Regulations relating to the allocation of payments which generally require that where a
facility is financed from two or more sources, payments with respect to that facility must
be allocated among the sources according to the relative amount of proceeds of each such
source. Here again, the 1986 Tax Act legislative history referenced above would allow for
allocation of both private use and private payments to the equity-financed portion of
facilities.
Transmission facilities are often financed in part with equity and in part with debt.
In addition, in anticipation of contracts for transmission, a MOU may redeem part of its
debt with equity or taxable bonds. The regulations should recognize that private use is
permitted with respect to facilities to the extent financed with other than tax-exempt
bonds. For example, if a particular transmission line is financed 75 percent with
tax-exempt bonds and 25 percent with taxable bonds or equity, subsequent private use of 25
percent of the capacity on such line should not result in any of the bonds having to be
redeemed. If the facility had been 100 percent tax-exempt financed and subsequently 25
percent of it is privately used, then only 25 percent of the bonds would have to be
redeemed. 75 percent of the facilities could continue to be financed with tax-exempt
bonds. The order in which the equity or taxable bonds are applied to finance the
facilities should not change the percentage that can be tax-exempt bond financed.
Similarly, recognizing the ability to have 10 percent private use, if 60 percent of the
facility is to be used by the MOU and 40 percent is used by private persons, then
approximately 66 percent of the facility can be bond financed and 34 percent would have to
be financed with taxable debt or equity. Consistently, if 100 percent of the facilities is
bond financed and 40 percent becomes privately used, the issuer should only be required to
retire 34 percent of its debt, not 40 percent. Again, the order in which the private use
arises, particularly in a changing industry, should not change the amount of facilities
which can be tax-exempt bond financed.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3
Examples 5 and 6 of Section 1.141-14(b)
Should Be Modified
Example 5 concludes that where 30 percent of the output of a facility is taken by a
private utility and 70 percent by a governmental utility and each party pays its
proportionate share of the costs, the allocation of the 30 percent private use portion to
the taxable financing having a weighted average life of 15 years does not reflect economic
substance where the tax-exempt financing has an average life of 26 years.
The example misconstrues the intent of the private activity limitations, which is to
limit the amount of tax-exempt financing rather than to specify the type of financing
arrangements that may be entered into. This is clear from the example in the legislative
history, incorporated into the Temporary Regulations, of the $500,000,000 plant. The
example concludes that only $465,000,000 of bonds may be issued on a tax-exempt basis. It
says nothing about how the remaining 35 million is to be financed. Reg. §1.141-8T(c).
Example 5 does not state what would have happened if the issuer had financed the
transaction with 30 percent equity and a tax-exempt financing having an average life of 26
years. However, based on the $500,000,000 example in the legislative history, it must be
possible to finance the facility in that manner. If an issuer finances 30 percent with
equity and 70 percent with debt, there is no rule that the equity cannot be
"amortized" faster than the debt; that is, that the debt could be interest only
for some period of time or involve slower amortization than level debt service in the
early years so as to allow a return of all or some part of the equity. There is no reason
taxable debt should be treated less favorably than equity.
Example 6 indicates the peril of attempting to dictate how parties acting at
arms-length should negotiate their deals. In that example, the allocation is upheld where
the private utility pays all the taxable debt service and the MOU pays all the tax-exempt
debt service. This ignores the fact that, depending on the term of the taxable debt and
the relationship of taxable to tax-exempt rates, the private utility might pay less than
it would have had it paid 30 percent of all debt service, because the taxable debt service
is shorter than the tax-exempt. The regulations should leave these matters to arms
length negotiation.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part VIIIh | Part VIIIi | Part VIIIj | Part VIIIj3
Financial Contracts
The Preamble to the Temporary Regulations requested comment upon the proper treatment
of options. There are also other emerging financial transactions that may have relevance.
We are not in a position to deal exhaustively with these matters, but we offer the
following comments.
Purely Financial Transactions.
In general we believe that financial transactions that hedge positions but do not involve
the actual use of output of facilities should be disregarded. One example of this type of
transaction is a swap from a fixed price to a variable price based on notional amounts of
energy. In such transactions, no actual energy changes hands nor even need be generated.
We believe such transactions should be disregarded.
Transmission Congestion Charges.
Another example of a financial contract that should be disregarded as not involving the
use of facilities to which they seemingly relate is the Transmission Congestion Charge
("TCC").
At least under some models, TCCs are not charges for transmission service at all.
Rather, they are increased costs of power over and above the cost of generation and
transmission that are caused by reason of the unavailability of transmission and that are
collected from purchasers of electricity and paid to the holders of the TCCs. Because the
TCCs do not involve actual transmission, they can be held by persons other than
transmission owners and, in fact, synthetic TCCs can be traded.
One place where TCCs are being used is New York. We have enclosed a description of the
New York TCCs as Appendix C because we believe it is similar to what is being, or will be,
done elsewhere. This description indicates that these types of arrangements are purely
financial and are not tied to any provision of transmission service.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part VIIIh | Part VIIIi | Part
VIIIj | Part VIIIj3
Options. Options where the MOU
agrees to purchase power or energy when put to it generally do not involve the use of the
MOUs facilities and should not give rise to private activity bond concerns. Options
where the MOU agrees to sell power or energy pursuant to an option to purchase may,
however, give rise to such concerns. If the option, when entered into, is at a bargain
price such that there is economic compulsion that it be exercised, the option may be
analyzed under the underlying arrangement rubric of the Subparagraph 5 Regulations or the
substantial certainty of payment rule consistent with the interpretation we have suggested
in these comments. Authorities distinguishing options from disguised sales are also
relevant. Where the option price is such that there is no substantial certainty of
exercise, however, it is hard to see how the option in and of itself could pass the
benefits and burdens of ownership to the option holder.
A second level of analysis may, however, be required depending on the effect of the
exercise of the option. If the exercise of the option itself creates a long term
obligation that would itself be taken into account, the fact that it arose from an option
should be immaterial.
Part VIII | Part
VIIIc | Part VIIId | Part VIIIf | Part VIIIh | Part VIIIi | Part
VIIIj | Part VIIIj3 | Contents |