COMMENTS ON
REGULATIONS UNDER SECTION 141
OF THE CODE AS THEY RELATE TO OUTPUT FACILITIES
Part II | Part IIb | Part
IIc | Part IIc2 | Part IId | Part
IIe | Part IIf | Back to Contents
SPECIFIC COMMENTS ON
PROVISIONS REGARDING USE OF GENERATION FACILITIES
Benefits of Ownership
General Comments. The benefits of ownership test provides that the benefits
of ownership exist where "the contract gives the purchaser (directly or indirectly)
rights to capacity of a facility on a basis that is preferential to the rights of the
general public."9
The reference in the definition to "rights to capacity" is useful in that it
indicates that sales of energy do not pass the benefits of ownership. "Energy"
sales have traditionally been non-firm transactions involving the sale of energy if
available, with only limited payment for the energy beyond direct costs of production
(fuel and other operating costs). Beyond the exclusion of energy sales, however, the
definition lacks clarity. The only discussion of what constitutes preferential rights and
thus the benefits of ownership is in Example 2 of section 1.141-7T(h) of the Temporary
Regulations, which states that a requirements contract must be taken into account because
it provides the purchaser with "substantial benefits of ownership (rights to
capacity)." The regular general public customers of the city in the example almost
certainly have "rights to capacity" that are no more interruptible than that of
the investor-owned purchaser. What then are the preferential rights of the purchaser that
are a benefit of ownership? There are no facts suggesting that price was the factor.
"Preferential rights" may be relevant in cases involving physical possession,
but we do not think "preferential rights" is an adequate concept for determining
whether substantial benefits of ownership are passed through a service contract. Rights at
least somewhat akin to those of a lessee should be required, and, as discussed elsewhere,
we think the factors enumerated in section 7701(e) of the Code, if not controlling, are
relevant in this regard.
Application to Joint Action Agencies.
Section 1.141-7T(c)(2) of the Temporary Regulations provides that an output contract
transfers substantial benefits of owning a facility if the contract "gives the
purchaser (directly or indirectly) rights to capacity of the facility on a basis that is
preferential to the rights of the general public." Many joint action agencies and
other similar governmental entities with municipal members sell only at wholesale. Often
this limitation on their scope of operation is imposed by state law. Under the Temporary
Regulations, because these entities do not sell to the general public, every contract
entered into by such an entity, no matter how subordinate to other obligations, would be
preferential to the rights of the general public and would meet the benefits and burdens
test, whereas a comparable contract entered into by a retail utility might not. If the
"preferential rights" concept is retained, it is suggested that this matter be
clarified by adding the following language to the end of section 1.141-7T(c)(2):
For the purposes of this section, a contract of a governmental wholesale supplier of
electricity gives the purchaser rights to capacity of the facility on a basis that is
preferential to the rights of the general public if the right is preferential to the
rights of the general public served by governmental purchasers of the governmental
wholesale supplier.
Part II | Part IIb | Part
IIc | Part IIc2 | Part IId | Part
IIe | Part IIf
Burdens of Paying Debt Service
General Comments. The burdens of paying debt service test is met under the
Temporary Regulations to the extent that the issuer reasonably expects that it is
"substantially certain that payments will be made under the terms of the
contract."10
While the test refers only to the "terms of the output contract," it appears
from the rules regarding requirements contracts that the surrounding circumstances must be
evaluated as well.
As presented, the "burdens" test is reasonably consistent, in keeping with
Congressional intent, with prior law. The application of such test under other portions of
the Temporary Regulations, however, appears to depart significantly from interpretations
under the Subparagraph 5 Regulations. For example, under the Temporary Regulations,
payment obligations on a 1-year contract for one percent of the output of a facility may
apparently be considered "substantial" burdens of ownership even though such
payments represent considerably less than 1% of total debt service on bonds having, for
example, a 30-year term. (See discussion below under "Short-Term Contract Safe
Harbor".)
Many members of the Committee commented on the need for clarification of the rule that
payments be substantially certain. Given that the basic concept is "burden" of
debt service, we think that generally the obligation to pay should rise to the level of a
take or take or pay contract or guaranteed payment, as under prior law. Lesser levels of
obligations should be taken into account only in the rare or exceptional case, such as
where the transaction is so clearly beneficial to the purchaser at the time it is made
that there is no question that the payments will be made. The basic test should remain
whether the burdens of debt service are passed, and the substantial-certainty-of-payment
concept should operate more along the lines of the underlying arrangement rule of the
prior regulations.
We note in addition that this provision is a part of the IRS reversal of its position
on requirements contracts that is discussed in the following section.
Payments on Contract Termination.
The Temporary Regulations provide that the burdens of paying debt service are met
"for example
if payments must be made upon contract termination." Reg.
§1.141-7T(c)(2)(ii). Similarly, the provision regarding retail requirements contracts
refers to "payments that are not contingent on the output requirements of the
purchaser." Reg. §1.141-7T(c)(4)(iii).
Many contracts for the sale of output involve construction of minor facilities such as
substations for the purpose of facilitating the delivery of output. It is not unusual for
the purchaser of the output to agree to make payments based on the cost of these
improvements if service is terminated before the cost is amortized. In such a case, the
benefits and burdens test should be treated as met with respect to the improvement, but
that does not mean that the benefits and burdens test is met with respect to the
generating facility that supplies the output. Accordingly, we believe the reference to
payments in the two above-cited regulatory provisions should be followed by the phrase
"properly allocable to the output facility."
In a competitive environment, it seems likely that many retail contracts will contain
minimum terms and termination fees for early termination, as is the case with similar
services such as cellular phone service. Those types of fees should not be treated as
causing the burdens of paying debt service test to be met.
The comments in the preceding two paragraphs are also applicable to retail requirements
contracts.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId | Part
IIe | Part IIf
Wholesale Requirements Contracts
General Comments. A wholesale requirements contract is taken into account
"only to the extent that, based on all the facts and circumstances, the contract
meets the benefits and burdens test."11
The Temporary Regulations specify "[s]ignificant factors that tend to establish that
the benefits and burdens test is met" under the rule.12
The factors specifiedthe significant indicators of stability of the customer base,
that the contract covers historical requirements, and that the contract contains an
agreement not to acquire other resourcesdo appear to be factors that provide some
indication that the benefits and burdens test is met. However, these factors in and of
themselves do not necessarily mean that the purchaser has taken on the burden of ownership
and debt service or received a benefit of ownership. Further, the regulation is a
substantial shift from prior law, as reflected in the Subparagraph 5 Regulations, which
followed PLR 7108270510A, supra, and in PLR 8240049 (July 6, 1982) and PLR 9125007
(Mar. 15, 1991), which have been relied upon by a number of very substantial issuers,
particularly with respect to contracts with rural electric cooperatives. There is no
suggestion in the legislative history (not even the gratuitous phrase concerning
requirements contracts with investor-owned utilities in the Joint Committee Report)13 indicating Congress intended to
upset these longstanding, very substantial arrangements.
The status of requirements contracts is a difficult policy issue. We are not prepared
to say that every requirements contract between municipal and investor-owned utilities
must be permitted. We are concerned, however, that the Temporary Regulation tests are not
administrable, and that their application will change with the passage of time because of
gradually changing facts. In addition, at least one significant factor, the term of the
contract, is not specified as a factor.
If the factors are retained in their present form, they will be difficult to apply
other than adversely. For example, with respect to the test of whether a contract covers
historical or projected requirements, requirements contracts typically cover either all
requirements or all requirements above those served from a specific source. The contract
thus will normally cover historical requirements. It will also cover projected
requirements in that it will cover requirements arising in the future. Accordingly,
although the parties may be relying heavily on the projected requirements, this factor
would appear to be met in the typical case.
The factor relating to whether the customer base has significant indications of
stability "such as large size, diverse composition and a substantial residential
base" raises the question "compared to what?" These considerations will be
very difficult to apply, either by bond counsel or by the IRS in private rulings or on
audit, in the absence of some reference points. Moreover, the size, diversity and
residential component may become largely irrelevant in the context of open competition,
when such objective factors as efficiency and subjective factors like advertising prowess
may be more relevant.
Finally, the factor relating to an agreement not to construct or acquire other
resources elsewhere would, in its present form, always point to private use. All
requirements contracts by their very nature contain some limitation on the ability of the
purchaser to go elsewhere for power. Thus, if retained, this factor needs to be refined.
For example, a requirement that the purchaser give reasonable notice, such as five years,
before obtaining another source of its requirements is far less significant than a
provision that precludes him from doing so for the life of a long term contract.
Similarly, the term of a contract ought to be a material factor in determining whether
a contract provides real benefits and burden, as recognized in the T.D.7199 file
memorandum cited in note 3. A requirements contract of short term duration, even three or
five years, provides no real transfer of benefits and burdens because such short term
arrangements provide no protection against market shifts in the context of 3040 year
financings of 4050 year assets.
Finally, two of the factors specified in the Temporary Regulations, whether the
contract covers existing or projected requirements and the stability of the customer base,
will likely change over time.
Thus, like many of the other new tests in the Temporary Regulations, these provisions
raise issues as to when the tests are to be applied. For the reasons set forth in detail
under "Time for Applying TestsEffect of Involuntary Changes," we believe
that, if these tests are retained, the determination as to the status of any contract in
existence at the time of a new money financing should be made either at the time the
contract is entered into or at the time of issuance of new money bonds to finance a
facility, and that subsequent changes in the nature of the customer base or other factor
being tested should not adversely affect that determination with respect to any subsequent
refinancings of that facility.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId | Part
IIe | Part IIf
Transition Rule Regarding Wholesale
Requirements Contracts. An extension of the term of a requirements contract
should only be considered a new contract starting with the first day of the additional
term, not from the date the extension is agreed to. This principle is important since
contracts are often extended significantly ahead of the time they expire because of the
need for forward planning.
The Temporary Regulations provide that a contract will be treated as a new contract if
"other material terms" to the contract besides a change in parties or term are
modified.14 This rule is too broad. A change
to a material term of the contract which does not change the concept of the amount of
electricity covered, e.g. the purchasers requirements, or the length of the
contract, should not be considered a new contract. In this era of change in the electric
industry, there will likely be many modifications required to material terms of existing
contracts which, while significant, do not change the scope of the requirements covered or
the term of the agreement. Such modifications should not be treated as creating new
agreements. In addition, a change in parties that arises by reason of a merger or
acquisition should not give rise to a new contract for this purpose.
Relationship of Requirements Contract Rules to
Other Rules. It appears that the requirements contract rules are intended
as exclusive rules, but the Temporary Regulations do not make this clear. For example, a
requirements contract that is grandfathered under the rule of section 1.141-15T(f)(2),
protecting contracts entered into before February 23, 1998, literally could run afoul of
the rule of section 1.141-7T(c)(2)(iii), relating to pledged contracts. Accordingly, the
regulations should be amended to make clear that the requirements contract rule is an
exclusive rule, or to specify those rules, if any, that might override it.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId | Part
IIe | Part IIf
Retail Requirements Contracts
Section 1.141-7T(c)(4)(iii) of the Temporary Regulations provides that a retail
requirements contract generally will not be treated as meeting the benefits and burdens
test of section 1.141-7T(c)(1). Such a contract may, however, be treated as meeting the
benefits and burdens test to the extent that the contract "contains contractual terms
that obligate the purchaser to make payments that are not contingent on the output
requirements of the purchaser (such as significant termination payments)
."15 The Temporary Regulations state
that retail requirements contracts do not meet the benefits and burdens test "because
the obligation to make payments on the contract is contingent on the output requirements
of a single user."16
Thus, the requisite certainty of payment is missing, even if the business of the retail
customer is economically healthy and the customer has no present plans to change or
terminate operations.
The Temporary Regulations in their current form should be interpreted as permitting
retail requirements contracts to contain reasonable damages provisions or reasonable
termination provisions without causing treatment as a "bad" output contract,
provided such damages or termination provisions are payable only in circumstances of
default or termination while the purchaser continues to have requirements within the
meaning of the contract. We believe this is the correct approach.
The essence of a requirements contract is that the purchaser must purchase its
requirements from the supplier, if it has any. It seems self-evident that such a contract
can provide for damages in the event of a breach. Silence on this point in the contract
would imply damages at law in any event. An explicit prohibition on damages for breach
would imply that the contract must be unenforceable, in which case the rule would serve no
purpose. Moreover, if the theory of the rule is that payments under the contract are not
sufficiently certain to meet the private payment testpresumably because a single
retail purchaser can fail to have requirements for a variety of reasonsthat logic is
as applicable to the defaulting purchaser as to the nondefaulting one. In addition, a
reasonable liquidated damages provision should also be permitted; parties should not be
forced to litigate their damages. Finally, contracts of this type should be permitted to
have termination clauses with reasonable buy-out payments, which analytically are no
different from liquidated damages provisions without the "default." We emphasize
again that this would only be in the context of default or termination by a retail
purchaser that otherwise has requirements that would be covered by the contract were no
default or termination to occur.
The Temporary Regulations generally do not require amendment to reach this result. A
contract provision that obligates the purchaser to make payments when its requirements are
reduced or eliminated would "obligate the purchaser to make payments that are not
contingent on the output requirements of the purchaser
or that obligates the
purchaser to have output requirements." A contract provision that obligates the
purchaser to make payments when it defaults or terminates the contract only when it still
has requirements does not.
If the Temporary Regulations are modified to clarify this point, however, we recommend
against trying to write specific damages or termination provisions that would be
permitted. There are many formulations of such contract provisions. It should be
sufficient for the Treasurys purposes that the damages or termination provision be
reasonably related to the purchasers obligation that is being discharged.
Our comments on termination payments on page 19 are also applicable to retail
requirements contracts.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId
| Part IIe | Part IIf
Exception for Swapping and Pooling
This provision provides generally that agreements for pooling and swapping do not
result in private business use to the extent amounts exchanged are approximately equal and
the purpose is to satisfy different peaks, create diversity, or enhance reliability; this
is a substantial improvement over the more restrictive provision of the 1994 Proposed
Regulations.17 Three additional points should be
considered, however.
First, there may be purposes other than the purposes specified which would cause a
municipal utility to enter into a swapping arrangement. Consideration should be given to
eliminating the purpose requirements or adding the phrase "or other bona fide
governmental purpose" to the list. To the extent the value of the amounts exchanged
are equal, there is no net private use, regardless of the purpose of the exchange.
Second, the Temporary Regulation is not entirely clear whether the exception is limited
to transactions involving payments in kind through the return of power. There appears to
be no reason to treat seasonal exchanges (in which the party buying during the first part
of the year pays cash and receives cash in the second half) less favorably than those
where the party simply returns the power in the second half of the year. In addition, we
understand that annual cash settlement on long term swaps is common. We assume that
exchanges with annual cash settlements would only involve private use to the extent the
municipal utility is a net payee and the arrangement otherwise meets the benefits and
burdens tests.
Third, three-cornered and multiple-party transactions should also be able to qualify
where the effect on the municipality is similar to that of a two-party swap.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId
| Part IIe | Part IIf
Three Year Stranded Cost Rules
Stranded cost recovery may arise because state law allows a utility to charge its
customers or transmission customers higher rates to recover excessive costs of its
facilities as part of a transition to deregulation or because FERC regulations allow the
utility to negotiate with a customer who is ceasing to be a customer to attempt to recover
costs incurred with respect to the customers load that will then be
"stranded." Thus, the focus of the provision on "the purchase of
output" and "all of the output sold" may be inappropriate.
It is not clear why the term of the transactions should be limited to three years in
view of the distressed nature of these transactions and the fact that they must either be
imposed by state law or negotiated at arms length, and the fact that the issuer is
required to take remedial action with amounts recovered. In addition, it is unclear why a
four year contract would be all bad while a three year contract is all good.
The requirement that the issuer not finance expenditures to increase generating
capacity with tax-exempt bonds should, at a minimum, not apply to bonds issued prior to
the effective date of the Temporary Regulations. More importantly, this requirement seems
to assume that any increase in capacity at a time of stranded costs is a dubious
enterprise. We are not so sure that is a correct assumption. The new facility might be
more economical and reliable than outmoded existing facilities. We recommend eliminating
this requirement.
Section 1.141-7T(f)(4)(iv) requires that all of the output sold be attributable to
excess capacity from open access. Again we think it should be sufficient that the issuer
was able to negotiate such an arrangement or that it was imposed by law or regulation or
entered into in anticipation of law or regulation.
Finally, section 1.141-7T(f)(4)(v) requires that "any stranded costs
recovered" be applied as promptly as possible in a manner consistent with the
remedial action requirements. We assume that the reference to "any stranded costs
recovered" means that remedial action is required only to the extent of the amounts
recovered.
Not all amounts recovered, however, will be available to retire bonds. Some amounts
will simply cover ongoing costs, including current debt service. The regulations should
clarify that only net amounts recovered must be used to retire debt.
Part II | Part IIb
| Part IIc | Part IIc2 | Part IId
| Part IIe | Part IIf | Back to Contents |